User Rights: Location: |
Project Administrator Company > Resources |
Click Company Tab
Click on the Resources option on the Menu to open Resource Management List
Click the Resource’s Full Name in the Resource Management List to open the Resource Profile page.
Click the Resource Rates tab on the Resource Profile Page to open the Resource Rates page.
If more than one Rate Schedule is being used by Your Company, click on the Tab with the Rate Schedule you want to work with
Select the Rate from the List and click the Edit icon to open the Edit Rate page.
Update the Rate Value and Effective Date as required. Keep in mind that the first rate in the list must not have an Effective From Date.
Click the Save button to save your changes.