User Rights: Location: |
Project Administrator Company > Resources |
Click Company Tab
Click on the Resources option on the Menu to open Resource Management List
Click the Resource’s Full Name in the Resource Management List to open the Resource Profile page.
Click the Resource Rates tab on the Resource Profile Page to open the Resource Rates page.
If more than one Rate Schedule is being used by Your Company, click on the Tab with the Rate Schedule you want to work with
Click the Add icon
Enter the Value of the new Rate and the date it is Effective From. Keep in mind that the first rate in the list will not have an Effective From Date.
Enter another rate if required by clicking on the Add Another Rate button and repeating Step 7.
Click the Save Button the save the new Rates.
How to Add Rates to Multiple Resources