Adding Rates to Multiple Resources

User Rights:

Location:

Project Administrator

Company > Resources

This technique can be used for one or more resources at a time and can be applied directly from the Resource Management List. 

Note:

This technique will not override rate values and effective from dates against resources.  Any added rates will be added to current schedule and will not override existing values.

  1. Click Company Tab

  2. Click on the Resources option on the Menu to open Resource Management List

  3. Select the Resources from the Resource Management List to have the new rates applied.

  4. If Multiple Rate Schedules are being used, select the Rate Schedule from the drop down list

  5. Enter the Value of the new Rate and the date it is Effective From.  Keep in mind that the first rate in the list will not have an Effective From Date.

  6. Enter another rate if required by clicking on the Add Another Rate button and repeating Step 5

  7. Click the Save Button the save the new Rates.